Laboratory quality control is the set of control checks run with every analytical batch to confirm that results are reliable before patient reports are released. Two or more levels of assayed control material are plotted on a Levey-Jennings chart, and Westgard multi-rules turn the pattern into a verdict. A 1-2s violation is only a warning, while 1-3s, 2-2s, R-4s, 4-1s and 10x each demand rejection. Precision and accuracy are separate, so a laboratory can be precisely and consistently wrong.
What you must remember
- Control levels: Run at least two levels, normal and pathological, with every batch, processed exactly as patient samples are.
- Levey-Jennings chart: Results are plotted in sequence against limits of ±1, ±2 and ±3 SD, and about 95 per cent of points should fall within ±2 SD.
- Westgard rules: 1-2s is a warning only. 1-3s (random), 2-2s (systematic), R-4s (random) and 4-1s (systematic) reject the run, and 10x (systematic) rejects after ten consecutive results on one side of the mean.
- Coefficient of variation: CV = (SD ÷ mean) × 100, and acceptable imprecision differs analyte by analyte, with electrolytes held tighter than enzymes.
- EQAS z-score: z = (laboratory value − assigned value) ÷ SD of the group. Within ±2 is satisfactory, 2-3 is questionable, and beyond 3 is unsatisfactory with documented corrective action.
- Calibration versus QC: Calibration fixes the signal-concentration relationship with traceable calibrators after a reagent lot change, major maintenance or drift. QC verifies daily that this relationship still holds.
- Error types: Random error scatters results, as with pipetting inconsistency or bubbles. Systematic error shifts them, as with miscalibration, reagent deterioration or expired standards.
- Accreditation: NABL requires documented IQC plus EQAS or proficiency testing participation for accredited tests, so both are needed, not either.
Working through a 2-2s violation
A 2-2s violation shows how the rules turn a control chart into a decision. The sequence below follows one Monday morning in a glucose assay, and each step has a defined purpose.
- Spot the pattern: Glucose control level 2, the pathological high, reads 2.4 SD below the mean. Yesterday the same control sat beyond −2 SD, so two consecutive results past the same limit trigger the 2-2s rule.
- Reject the run: The run is rejected, and all results since the last acceptable QC are held rather than released.
- Troubleshoot by likelihood: A new reagent lot was opened yesterday, so check the lot-to-lot bridge and recalibrate first. Then verify control expiry and inspect the analyser.
- Confirm recovery: After recalibration the control returns to −0.3 SD, and the held patient samples are re-run.
- Document the loop: The rejection, suspected cause, corrective action and re-run all enter the QC log, because an assessor reconstructs exactly this sequence.
A lone 1-2s point with no other violation calls for watchful progress rather than rejection.
Where the exam tries to catch you
Three distinctions carry most quality control questions in the examination.
- Trap: Treating a precise but consistently wrong result as a random-error problem. Correct: Picture four tightly clustered shots off the bullseye. An offset calibration reproduces the same wrong value every run, and recalibration against traceable material fixes it, not more repeats.
- Trap: Reading a control at −3.1 SD and a control alternating +2.3 then −2.2 SD as the same kind of error. Correct: −3.1 SD breaches 1-3s (random, reject), while alternating +2.3 and −2.2 SD breaches R-4s (random). Six consecutive results above the mean head toward 10x, a systematic shift.
- Trap: Assuming internal quality control and EQAS do the same job. Correct: Internal control proves today's run behaved, while external assessment proves results agree with peers. Competence demands both.
Frequently asked questions
What is a Levey-Jennings chart and how is it built?
A Levey-Jennings chart is a time-sequence plot of daily control values against the assigned mean, with ±1, ±2 and ±3 SD limits drawn on it. It reveals shifts, trends and random scatter at a glance.
Which Westgard rules reject a run, and what error type does each signal?
The rejection rules are 1-3s (random error), 2-2s (systematic error), R-4s (random error), 4-1s (systematic error) and 10x (systematic error). The 1-2s rule serves only as a warning to inspect further.
How are precision and accuracy defined with the CV formula?
Precision is reproducibility under repeat conditions, and accuracy is closeness to the true value. The coefficient of variation, calculated as CV = (SD ÷ mean) × 100, summarises imprecision.
What is a z-score in EQAS and how is it interpreted?
In EQAS, the z-score equals (laboratory value − assigned value) ÷ SD of the group. A z-score within ±2 is satisfactory, 2-3 warrants investigation, and beyond 3 is unsatisfactory with documented corrective action.
How does calibration differ from quality control?
Calibration establishes the measurement relationship using traceable calibrators at defined intervals or after events such as a reagent lot change. Quality control monitors every batch to confirm that this relationship still holds.